Location:
5441
Clinton Hwy., Knoxville, TN
size:
122,000
SQ FT
schedule:
A
grueling 7 week schedule (not 7 months)
from November 15, 2000 to January 8, 2001,
the coldest winder on record with average
temperature of 33.8°. Average work force
numbered 100 people, 12 - 1 6 hours per
day, 6 - 7 days per week.
Construction:
Renovation
of former Lowes Retail Center
to a Convention Center & Exhibition Hall |